Daher project
100% Done8 phases
Development
Location
Saha
Duration
16/06/2025 - 25/06/2025
Project Progress
100%Complete
7/8 Phases Completed
Current focus • Exterior Works
01
Phase 1
Assessment & Planning
Progress
100%
- Inspect the existing house
- Identify required repairs and upgrades
- Set the renovation plan and design
02
Phase 2
Permits and Contracts
Progress
100%
- Obtain municipal permits
- Finalize legal and administrative requirements
03
Phase 3
Demolition & Removal
Progress
100%
- Remove old flooring, tiles, partitions, and damaged elements
- Clear unwanted materials
04
Phase 4
Structural Adjustments
Progress
100%
- Modify or reinforce columns
- Reinforce Slab
05
Phase 5
Interior Rough In
Progress
100%
- Blockwork partitioning
- Electrical rough-in
- Mechanical (HVAC) and Plumbing rough-in
- Plaster
06
Phase 6
Exterior Works
Progress
99%
- External plaster and insulation
- Façade finishing
- Waterproofing
- Outdoor areas and landscaping
07
Phase 7
Interior Finishing
Progress
100%
- Flooring installation
- Painting and Decor
- Electrical & mechanical fixtures
- Doors, windows, aluminum, glass
08
Phase 8
Handover
Progress
100%
Site Cleaning and Handover
An Ancient Heritage House
The Daher family house was built in 1902. As part of Samana Company's efforts to preserve ancient heritage in villages, Third Home was commissioned to restore this building, taking into account its ancient heritage.